CLIENT COMMENDATIONS
Why do the best companies choose Sevenson?
TESTIMONIALS
“The project was bid with a projected schedule of about 30 months and designed to occur in two phases to ensure a mechanism to bring in a different contractor if Phase 1 did not go smoothly. Sevenson met or exceeded all expectations in Phase 1. Sevenson has proven it has the depth of expertise – including two dedicated maintenance personnel always on site – and breadth of large, specialty equipment. They have imported and assembled two 10-foot-diameter soil auger drill rigs from Germany and a custom made 165- foot one-pass trencher to install a hydraulic barrier wall down to 100 feet bgs. to contain impacts within the M&R station area. They are now driving an expedited schedule closer to 18 months in duration. Attention to detail by the onsite crew has allowed the project to continue at this pace despite hurricanes and blizzards, and all while paying strict adherence to PSE&G’s COVID-19 protocols.”
Jacques Benaroch, PE
Senior Project Manager
Former Harrison Gas Plant, Phases 1 and 2
“WSP acknowledges that Sevenson has performed very well on this project (technical + safety), has been hyper responsive to WSP/EPA requests, and has navigated a challenging supply market with success to keep the project on track for completion in 2022.”
Rod Pendleton, PG
Principal Project Manager
In-Situ Stabilization Remediation Project, Maryland
“Your work to cleanup the radiological contamination at the DuPont Chamber Works Site is complex and of the highest quality. You consistently employ innovative and cutting-edge techniques to achieve and surpass remediation goals. Our Close working relationship has continuously improved the program, resulting in a significant reduction of savings to the taxpayer.”
Carmelo Melendez
Director
DOE Legacy Management
“A team is only as good as all its parts and as our General Contractor you have done an incredible job executing our project.”
…. “The past year has been challenging for the Nation and the World. Most of the nation had a stoppage of work, and supplies and services were extremely difficult to procure. COVID health and safety restrictions were problematic, but somehow our DuPont Chambers Works project continued to move forward. The United States Army Corps 2021 Project Delivery Team (PDT) of the Year Award for Excellence for the DuPont Chambers Works FUSRAP Project, is truly a testament to the outstanding support and collaborative efforts of the Sevenson team. This award and the achievements that led to it have enhanced the reputation of Sevenson, the Philadelphia District, North Atlantic Division and the FUSRAP program. It is a great foundation for continued project success and nearly 1000 days without a lost time accident at this site is a great success by itself.”
LTC Ramon Brigantti,
Commanding Officer of USACE Philadelphia
“(Good things) happen when we, as a team, listen, plan and execute, and listen some more. It was a great outcome…. Thanks for all your hard work. It DOES show!”
Marc B. Okin, CPG
Remediation and Due Diligence Manager
NiSource, Inc.
“Sevenson worked collaboratively with the project team members (Engineer-of-Record, Independent Quality Assurance Team, EPA Oversight contractor) and overall performed exceptionally well.”
…Sevenson was retained by the Shaffer Landfill Remediation Trust to implement the capping remedy at the Shaffer Landfill (Iron Horse Park OU-2) in Billerica, Massachusetts. The landfill is located in a community deeply concerned with the potential short-term impacts associated with the implementation of the remedy (truck traffic, noise, and odors). The project was challenging in that an exceptionally large amount of imported material was required. Sevenson’s proactive planning, and aggressive approach to traffic management, and noise and odor controls resulted in a smooth execution with no community complaints. Sevenson worked collaboratively with the project team members (Engineer-of-Record, Independent Quality Assurance Team, EPA Oversight contractor) and overall performed exceptionally well.
Thor Helgason,
Shaffer Landfill Remediation Trust Project Coordinator
“Sevenson delivered the complex Bayou d’Inde/Lower Canal sediment remediation project on time, on budget, and most importantly safely.”
Sevenson delivered the complex Bayou d’Inde/Lower Canal sediment remediation project on time, on budget, and most importantly safely. As the work progressed over the two year period, the project truly became a team effort. Sevenson and its staff were a class act to work with.
Anchor QEA LLC
Wendell Mears, Bayou d’Inde/Lower Canal Sediment Remediation
“I can’t say enough for the job that Sevenson did over these last 10 years.”
I can’t say enough for the job that Sevenson did over these last 10 years. Technically Sevenson was our subcontractor, but for the day-to-day running of the construction project and working through the design plan details they were a true equal team partner. Sevenson proved steady in many trying times over the years with issues ranging from regulatory, construction, the weather and more, and always kept the ultimate goal in mind, finding ways to proceed in a productive and efficient manner. Sevenson’s group were true professionals and are great to work with. I would work with them anytime, anywhere.
ARCADIS U.S., Inc.
Michael F. Savage, P.E. Kress Creek and the West Branch
of the DuPage River
“Sevenson demonstrated an outstanding ability to work in a positive and constructive manner with all interested parties which has been critical to the success of this project.”
“…As the United States Environmental Protection Agency project manager, it is my responsibility to task the Army Corps of Engineers to perform environmental response activities at the Cornell-Dubilier Electronics Superfund (CDE) site. The Army Corps of Engineers then directs the contractor (Sevenson Environmental Services) to execute the work. Within the context of this working relationship, I provide the following recommendation for Sevenson at the CDE site.”
“I have had the pleasure of interacting with Sevenson since January 2011. The intrusive nature of the remediation at the CDE site has been a concern for EPA, local residents, commercial property owners and tenants, as well as elected officials.”
“…has demonstrated an outstanding ability to work in a positive and constructive manner with all interested parties which has been critical to the success of this project.”
“…has employed strong leadership and communication skills necessary to provide effective direction to multiple remediation crews deployed throughout the community.”
“…the high quality results of the environmental remediation and restoration work performed at the site.”
“On repeated occasions, EPA personnel have received positive comments and praise from residents within the affected community concerning the high quality of Sevenson’s work.”
United States Environmental Protection Agency Region 2
Diego Garcia, Project Manager Cornell Dubilier-Electronic Superfund Site
“I would like to recognize the professionalism, responsiveness, great attitude and cooperative spirit demonstrated by your entire team”
Successful completion of this project was critical to our client in meeting their regulatory obligations and as a Project Manager, I understand the significant technical challenges that Sevenson had to address due to the aggressive schedule and complexity of the site.
Sevenson not only met the required project schedule but completed all of the work within the original contract budget with no change orders. I believe this result was a reflection of the outstanding communication and project management that Sevenson dedicated to the project and your flexibility and willingness to work with us and our client to overcome unforeseen conditions.
I would like to recognize the professionalism, responsiveness, great attitude and cooperative spirit demonstrated by your entire team.
Golder Associates
Patrick T. Martin, P.E., BCEE SNPE – Vandemark Chemical Creek Bank Corrective Measures Project
“In addition to an excellent safety record for the project, all health, safety, and environmental aspects of the projects went without issue – no odor dust/complaints, compliant wastewater performance, no regulatory agency issues.”
“In addition to an excellent safety record for the project, all health, safety, and environmental aspects of the projects went without issue – no odor/dust complaints, compliant wastewater performance, no regulatory agency issues. The project drew good comments from USEPA and ACOE during weekly regulatory meetings and site walk-throughs. Also noteworthy is the fact that the project prepared for and successfully made it through Hurricane Sandy without major issues, resulting in a project restart within 2-3 days of gaining site access after the storm.”
“…the UOP Rutherford project involved great coordination, cooperation, and communications amongst the contractors to yield successful, safe, and sustainable results.”
Honeywell
Sam Visnic, CHMM UOP Rutherford Non-Time
Critical Removal Action Project
“Your team navigated through countless obstacles to achieve positive outcomes…”
“I want to thank you for assembling such a fantastic team of staff to implement the soil cleanup on the non-public properties of Newhall Street Neighborhood site in Hamden, Connecticut – the largest cleanup effort in the State’s history.”
“Your team navigated through countless obstacles to achieve positive outcomes…”
“…I sincerely appreciate the outstanding efforts taken by each member of your team, and am very proud of the work they performed…”
Connecticut Department of Energy & Environmental Protection
Ray Frigon
“Sevenson…worked well in a cooperative manner with the entire team…”
Sevenson…worked well in a cooperative manner with the entire team…Sevenson provided added value by suggesting changes in the approach that allowed us to…accelerate the schedule, completing the project in less than 2.5 years instead of the originally planned 5 years. These changes and others recommended by Sevenson provided significant savings to the project.
AMEC Environmental & Infrastructure
Nelson Walter, PE, LEP, LSP, PMP
Project Manager
“Olin appreciates the capable, professional, and cost-effective manner in which Sevenson consistently executed this project.”
Olin Corporation
David M. Share, P.E.
Director of Environmental Remediation
“APWA 2012 Project of the Year Award. This prestigious award would not have been possible if not for the superior construction services provided by Sevenson.”
Cecil County Government
W. Scott Flanigan, P.E. Department of Public Works, Elkton, MD
Director of Public Works
“Twice a year, as part of our Contractor Evaluation program, we issue report cards to contractors that have performed work during the prior 36 months.”
Contractor performance ratings are based on…the following work categories: environment, health and safety, quality, timeliness, administration and conduct of work. This information may be based upon reports by individuals who are responsible for overseeing your work…Performance ratings are measured on a scale of 1.0 (poor) to 5.0 (excellent) with a rating of 3.0 being satisfactory. Based on the factors available and taken into consideration, your current performance rating is 4.33.
Consolidated Edison Company of Gary Govenanti New York, Inc. Contractor Performance
“It has been a pleasure working with Sevenson to complete the Spring Valley FUDS arsenic removal program. The thoroughness and timeliness that they brought to each project makes Sevenson a reliable partner…”
U.S. Army Corps of Engineers
Dan Noble Baltimore District
Project Manager
“…Sevenson exceeded expectations on multiple delivery orders. They performed quality work in a timely manner. Both EPA and local officials were extremely satisfied with the work performed.”
Rick Robinson, EPA Region 2
“[Sevenson] provides our project with excellent site management of craft and execution of tasks. I find them professional, reliable, and conduct all operations with safety in mind.”
Shawn Andrews, USACE SLDA Health Physicist
“Your team has reached out to Praxair to effect a quality, on-time, within budget highly complicated feature (design-build utilities replacement) of the remediation…”
Chief-NY/PA Construction, CELRB
“Sevenson exhibited high quality workmanship throughout the project.”
Sevenson exhibited high quality workmanship throughout the project. Sevenson implemented an extensive Quality Control (QC) System to address this complex project. …The Sevenson on-site and home office management staffs were superb. …The entire Sevenson project team was professional in every way.
U.S. Army Corps of Engineers
Douglas M. Anderson, Administrative Contracting Officer Indiana Harbor and Canal Cutoff Wall
“[The] Contractor completed on-site remediation activities on schedule in light of an increase in the excavation footprint. Both home office and on-site personnel were accessible and ready to meet on short notice with USACE personnel to resolve differing site conditions in the field.”
Gerald DiPaola, CELRB COR
Rooted in Remedial Construction
Expanded into Environmental Dredging
Start a conversation about your upcoming project
(716) 284 - 0431
© 2021 Sevenson Environmental Services -
Privacy Policy | Sitemap
2749 Lockport Road | Niagara Falls, NY 14305
P: (716) 284 - 0431 | F: (716) 284 - 7645