Jersey City, New Jersey
Study Area 3 is a commercial/retail area of Jersey City, NJ, known as the Bayside Redevelopment Area. The site is bound to the east by Highway 440, to the north by Highways 1 and 9, to the west by the Hackensack River, and to the south by Clendenny Ditch. For the past century, the site was used for industrial activities. Hexavalent Chromium Ore Processing Residue (COPR) was stored and used as fill material on the site. Consequently, the COPR fill contaminated the site’s soil and groundwater.
Sevenson excavated 6,060 CY of hexavalent chromium-impacted soil, to depths ranging from 2–9 ft. BGS. Soil was excavated and transported, placed, and compacted for consolidation below the RCRA-type cap. Where excavations extended beyond approximately 4-ft. into the groundwater table, Sevenson performed dewatering operations to lower the local groundwater elevations. To prevent surface water accumulating within the excavation areas, sumps were installed and transferred impacted water to a 180-GPM WWTP, which treated and discharged >8.6M gallons of water. Sevenson installed a 2,547-ft. vertical hydraulic barrier wall of steel sheet piling around the site’s perimeter along a pump and treat system with recovery wells and a permanent WWTP. The purpose of the sheet pile wall and pump and treat system was to surround the impacted soil and prevent further migration of contaminants into adjacent areas. Sevenson installed a 7.5-acre, RCRA cap that included geosynthetic components, such as geocomposite venting, a 60-mil LLDPE geomembrane, and geocomposite drainage and demarcation layers. Restoration included the placement of a 6-in. cover of clean topsoil and establishing a vegetative cover over the cap area. The subgrade preparation, RCRA cap installation, and final cover were all installed during the summertime. As a result of Jersey City, NJ receiving nearly 12-inches of rain between June and August, Sevenson performed dewatering activities 24/7 during most of the summer months to ensure the job was completed on time and with no additional cost to the Client.