Napa, California
The Napa MGP was in operation from 1889 to 1924 but was shuttered after natural gas arrived in Napa. More recent investigations resulted in the development of a plan to remediate primary COCs including PAHs, naphthalene, benzene, petroleum hydrocarbons and cyanide.
Sevenson completed in-situ soil stabilization (ISS) of approximately 24,000 CY of contaminated soils using two 8-ft. diameter drill rigs to depths of 60-ft. below ground surface. Crews erected a temporary fabric structure (TFS) to house excavation activities and reduce dust and odor issues for the surrounding residential area and moved it to a new location on site while it was still constructed. A total of approximately 20,000 CY of soil was excavated from the Former Napa MGP Site under the TFS. Sevenson was able to save the client money by providing a value engineering method of pre-auguring drill columns and bringing in a second drill rig to increase production. This project received the 2024 PG&E ACE Award for Safety Excellence from our client.