Salina, New York
General Motors Corporation (GM) began operating its Inland Fisher Guide plant (GM-IFG Facility) in Salina in 1952. Operations there included metal die casting; nickel, chromium and copper cyanide electroplating; and stamping, polishing, buffing, painting, and machining. During the early 1960s, GM added injection molding operations. Metal finishing and die casting were subsequently reduced and replaced by injection molding by the early 1970s. PCB-containing hydraulic oil was used in production machines at the GM-IFG Facility until 1969. PCB-containing oil leaked from the machines to floor drains and sumps. This oil and other process waste was discharged to an on-site swale. The swale discharged to Ley Creek, where PCBs are found in the sediments. GM ceased all manufacturing operations at the GM-IFG Facility by December of 1993.
Sevenson performed precision excavation of contaminated soils from constrained areas at 19 residential properties adjacent to Ley Creek and downstream of the GM-IFG Facility. In total, we excavated 6,375 CY of contaminated soil from depths of 6-in. to 5-ft. BGS and coordinated the characterization and off-site transportation and disposal of TSCA and non-TSCA soils. Sevenson proposed and constructed an 80-ft. Mabey bridge that rerouted heavy equipment traffic away from the affected residential properties and minimized disturbances to the surrounding residents. This traffic diversion allowed Sevenson to avoid impacting the front yards of the affected homes. Additionally, crews conducted extensive site restoration of the properties including placing and grading clean backfill, planting sod and trees, and replacing other back and side yard features to restore each to its original condition.